11-12-2014, 10:27 PM
wednesday came and trenching for electric got delayed. the electric utility construction manager came and we have to work out how to get the power to the shop. have to avoid the septic line so it has to be adjusted a little.
the garage door company came about 10 and the last guy left about 9pm. they are mostly done but have to come and wire up the openers and finish the trim another time.
they look nice.
making some progress
tom
the garage door company came about 10 and the last guy left about 9pm. they are mostly done but have to come and wire up the openers and finish the trim another time.
they look nice.
making some progress
tom
2002 45'8" Newell Coach 608 Series 60 DDEC4/Allison World 6 Speed HD4000MH