08-11-2014, 10:05 AM
today there was a crew of ten concrete guys. they changed from a separate footer, stem and floor pour to a monolithic pour. the plumber was there to lay out the underground plumbing.
it will be dug and plumbed in the next 2 days and then once they have that done and they have the dimensions for the sill bolts/rods, they will do the pour. gee, maybe this week who knows.
i attached a few pictures that gave a little better perspective on the dimensions. had darlene stand in the back corner with her arms outstretched.
happy 1st saturday
tom
it will be dug and plumbed in the next 2 days and then once they have that done and they have the dimensions for the sill bolts/rods, they will do the pour. gee, maybe this week who knows.
i attached a few pictures that gave a little better perspective on the dimensions. had darlene stand in the back corner with her arms outstretched.
happy 1st saturday
tom
Former Owner 2002 45'8" Newell Coach 608 Series 60 DDEC4/Allison World 6 Speed HD4000MH