11-06-2018, 03:05 PM
howdy all,
today i took out my prosine 3.0 and started installing a magnum 2812 like alot of you guys have.
a few questions for you
i bought the battery monitor kit and the advanced control panel.
the battery monitor requires the unit be within 5 feet of the batteries. it has a 4 wire harness that goes to each side of the shunt and plus and minus on the batteries. it also says it should not be installed in an enclosed area or in where the batteries are.
i see no way of putting it anywhere else. did you guys just put the shunt on top of the batteries?
the prosine had a mounting bracket that held it about an inch off the wall. the magnum is mounted directly to the wall. no standoffs. did you make a bracket or some kind of standoff or just put it directly on the wall?
thanks
tom
today i took out my prosine 3.0 and started installing a magnum 2812 like alot of you guys have.
a few questions for you
i bought the battery monitor kit and the advanced control panel.
the battery monitor requires the unit be within 5 feet of the batteries. it has a 4 wire harness that goes to each side of the shunt and plus and minus on the batteries. it also says it should not be installed in an enclosed area or in where the batteries are.
i see no way of putting it anywhere else. did you guys just put the shunt on top of the batteries?
the prosine had a mounting bracket that held it about an inch off the wall. the magnum is mounted directly to the wall. no standoffs. did you make a bracket or some kind of standoff or just put it directly on the wall?
thanks
tom
2014 Haulmark 40' Super C on Freightliner Cascadia ISX15 Easton 13 speed
Former Owner 1990 38' Newell Coach 236 8V92
Former Owner 1999 45'8" Newell Coach 526 Series 60
Former Owner 2002 45'8" Newell Coach 608 Series 60